Wind Tower I Progress Graph

Graph Legend

Superstructure FINISHED.
Concrete slab casted
Block work
MEP & finishing
in progress
 

Rera Monitoring
2015-03-10 Report

• Construction Updates

Construction Progress Report on February 07, 2015.

  • " Wind Tower I " Projects progress on February 07, 2015.

    Superstructure FINISHED. Concrete slab casted, Block work, MEP & finishing in progress

    Please see more photos...



Registration of Wind Projects under Tanmia Program:

We are pleased to inform all esteemed investors that Wind Tower I and Wind Tower II projects are registered under Tanmia Program( http://www.dubailand.gov.ae/English/Tashjee/tanmya_objectives.aspx), a governmental revitalization plan for the Real Estate Market focusing on under-construction projects launched by Dubai Land Department.
We were introduced to this program in last November and after reviewing its targets, as we were determined to work our investment/development plans under supervision of RERA and DLD, we decided to take this opportunity. Fortunately, Tanmia's officials have been very supportive to our projects and finaly we could register the projects under this program last week.
Furthermore, till the date, two of our candidate investors have already registered their companies under Tanmia as investment parties for Wind projects and the third investor is preparing required documents for the same. They are seriously trying to finish program's formalities to get the final approval and start their activities as "approved investor".

Submission of financial audit reports:

The financial audits for Wind Tower I and Wind Tower II projects finished and the reports were submitted to RERA during the timeframe on 30th January 2012. The RERA-registered auditor company, reviewed all financial transactions and legal documents pertinent to whole projects and unit-owners since beginning till end of 2011 and prepared comprehensive reports as per RERA rules and requirements.

Important Announcement:
Recent Development Activities and Timeline

We are delighted to inform Wind Towers' esteemed investors of recent development activities regarding Wind Tower I and Wind Tower II projects...read more

Happy Eid Al Fitr to all Muslims!

We wish that Allah's blessings light up the path and lead to happiness, success and peace. Eid Mubarak!

Change of contact details

We would like to inform all esteemed Wind investors that due to some changes in telephone lines, our new contact details are as below:
Tel: +971-4-3809219
Fax: +971-4-3212194
Mobile: +971-55-5986836 & +971-55-3529809
In addition to main office of "Wind One Inc." and "Wind Two Inc." Companies, we set-up a new office near the projects for better and easier coordination. For meetings, please coordinate through customer.service@windint.com or customer.service@windtowers.net emails.

Sales and marketing network for generating cash flow

Global economical crisis has had destructive effects on real estate market and forced a lot of construction projects to cancel, stop or on-hold situation. The direct impact of this crisis on Wind Tower Projects is that many investors/purchasers have been unable to fulfill their financial commitments and about AED 33,000,000 is overdue since 2007 till the date and total payable to projects till completion is equal to 146 Million Dirham. During the last two years, developer has invested in the projects without receiving overdue amounts from purchasers. Consequently, projects faced financial problems and we had no other option except to slow-down at the end of 2010.

We believe that investors/owners (including developer who owns whole projects) does not benefit from current situation and everyone should endeavor their best to find a way forward. Accordingly, we have had numerous meetings with RERA, individual buyers, and investors’ representatives and some negotiation with investment/contracting companies regarding current problems and finally have come up with the followings:

1- “Wind One Inc” and “Wind Two Inc” companies (developers of Wind Tower I & II) are ready to sell their stock (unsold) units with very competitive (below market) price and inject all income into the projects through ESCROW Accounts.

2- Finding a joint-venture contractor who will be paid a minimum amount (about 3.5 million Dhs) for restarting construction work (against issuance of bank guarantee) and monthly payments equal to 2 Million Dhs. The balance will be settled through transferring some units from the projects to them. Fortunately, we have reached to final stages of negotiation with one of well-known contractors in Dubai and we are reviewing and evaluating their quotation now.

3- Finding new investment company to solve projects financial issues by injecting AED 10 Million bank guarantee and AED 24 Million cash in next 12 months (monthly AED 2 million) as bridge fund. In return, we will transfer 50 percent share of wind stock units with minimum total value of 99 Million and maximum total value of 160 Million Dirham.

Hereby, we are kindly requesting all esteemed investors to unify all goals and efforts into solving cash-flow problem through above items and start a marketing campaign through their network for selling available units or attracting new investors for the projects.

All required information and documents will provided upon your request through customer.service@windint.com. All constructive suggestions and opinions in this regard are welcome.

For and on behalf of
WIND ONE INC. LIMITED” & “WIND TWO INC LIMITED” Companies

Important Events:

CIRCULAR
Establishing Owner Association for Wind Tower Projects

A meeting was held on 28th February 2011 between a group of investors’ representatives (including Messrs. Jayesh Vishun Sajani, Dr. Debabrat Changkakoti, Raju Mansukhani, Naresh Dogra, Michael Sabzerou) and developer of Wind Tower I & II to discuss about current situation of the projects and the way forward.

It was suggested by the attendees to form Owner Association through a democratic election.  Therefore, every investor who is interested to be a member of the board they are kindly requested to send us their plan for projects development and moving ahead from current situation. All information will be shared with other investors and finally an electronic election will be done and five candidates will be elected and nominated as members of board based on the votes.

This circular is considered as official announcement for the above subject and candidates should forward their plan for projects development through customer.service@windint.com or fax no. +97144468610 within one week from date of this letter before 23th March 2011.

On behalf of:
“Wind One Inc.” and “Wind Two Inc.” companies

Office no. 113, Building no. 5, Dubai Internet City, Dubai-UAE
Tel: +97144468620
Fax: +97144468610
Email: customer.service@windint.com
Web: www.windtowers.net

Important Events:

Formation of “Wind Steering Committee”

We are pleased to inform you that a Steering Committee has been formed consisting of representatives of the following parties in order to move ahead with the Wind Tower 1 and Wind Tower 2 projects:

  • RERA (The Real Estate Regulatory authority)
  • DMCCA (Master developer of JLT)
  • Wind Projects developers (“Wind One Inc.” and “Wind Two Inc.” companies)
  • Wind Investors’ representatives

This committee is responsible to supervise project development activities to overcome current problems and find a way forward. Committee’s meetings will be held every 4-6 weeks and MOM will be circulated to all investors for their information. As per the last meeting, DMCCA is responsible for Project Management to coordinate construction work through selecting/nominating a professional engineering third-party PM and introducing it to the committee..
We trust that with formation of the Wind Steering Committee under supervisions of RERA and continual support of our esteemed investors, construction work will start soon and the project will be completed. We would like to express our sincere thanks and appreciation for your patience and support.

Latest news from the construction site

4th of October 2010
Plastering Retail area wall in b-1 ,Blockwork on 2nd floor ,Fire Fighting & Alarm system testing & commisioning is working on 14th floor in Progress

3rd of October 2010
Plastering Retail area wall in b-1 ,Blockwork on 2nd floor ,Fire Fighting & Alarm system testing & commisioning is working on 14th floor in Progress

2nd of October 2010
Plastering Retail area wall in b-1 ,Blockwork on 2nd floor ,Fire Fighting & Alarm system testing & commisioning is working on 14th floor in Progress.

1st of October 2010
Blockwork started on 2nd floor ,MEP work ,Fire Fighting & Alarm system testing & commisioning is working on 13th floor in Progress.

30th of September 2010
Blockwork started on 2nd floor ,MEP work ,Fire Fighting & Alarm system testing & commisioning is working on 13th floor in Progress.

29th of September 2010
Blockwork started on 2nd floor ,MEP work ,Fire Fighting & Alarm system testing & commisioning is working on 13th floor in Progress.

27th of September 2010
Blockwork started on 2nd floor ,MEP work ,Fire Fighting & Alarm system testing & commisioning is working on 13th floor in Progress.

26th of September 2010
Blockwork started on 2nd floor ,MEP work ,Fire Fighting & Alarm system testing & commisioning is working on 13th floor in Progress.

23th of September 2010
Blockwork started on 2nd floor ,MEP work ,Fire Fighting & Alarm system testing & commisioning is working on 13th floor in Progress.

22th of September 2010
Blockwork started on 2nd floor ,MEP work ,Fire Fighting & Alarm system testing & commisioning is working on 13th floor in Progress.

20th of September 2010
Blockwork started on 2nd floor ,MEP work ,Fire Fighting & Alarm system testing & commisioning is working on 13th floor in Progress.

19th of September 2010
Blockwork started on 2nd floor ,MEP work ,Fire Fighting & Alarm system testing & commisioning is working on 13th floor in Progress.

18th of September 2010
Blockwork started on 2nd floor ,MEP work ,Fire Fighting & Alarm system testing & commisioning is working on 13th floor in Progress.

16th of September 2010
Blockwork started on 2nd floor ,MEP work ,Fire Fighting & Alarm system testing & commisioning is working on 13th floor in Progress.

14th of September 2010
Blockwork started on 2nd floor ,MEP work ,Fire Fighting & Alarm system testing & commisioning is working on 13th floor in Progress.

13th of September 2010
Blockwork started on 2nd floor ,MEP work ,Fire Fighting & Alarm system testing & commisioning is working on 13th floor in Progress.

12th of September 2010
Blockwork started on 2nd floor ,MEP work ,Fire Fighting & Alarm system testing & commisioning is working on 13th floor in Progress.

11th of September 2010
Blockwork started on 2nd floor ,MEP work ,Fire Fighting & Alarm system testing & commisioning is working on 13th floor in Progress.

7th of September 2010
Blockwork started on 2nd floor ,MEP work ,Fire Fighting & Alarm system testing & commisioning is working on 13th floor in Progress.

5th of September 2010
MEP work ,Fire Fighting & Alarm system testing & commisioning is in Progress.

2nd of September 2010
MEP work ,Fire Fighting & Alarm system testing & commisioning is in Progress.

31th of August 2010
MEP work ,Fire Fighting & Alarm system testing & commisioning is in Progress.

28th of August 2010
MEP work ,Fire Fighting & Alarm system testing & commisioning is in Progress.

24th of August 2010
MEP work ,Fire Fighting & Alarm system testing & commisioning is in Progress.

18th of August 2010
MEP work ,Fire Fighting & Alarm system testing & commisioning is in Progress.

14th of July 2010
Block work & plaster work & MEP work ,fire fighting & alarm system testing & commisioning is in Progress.

13th of July 2010
Block work & plaster work & MEP work ,fire fighting & alarm system testing & commisioning is in Progress.

12th of July 2010
Block work & plaster work & MEP work ,fire fighting & alarm system testing & commisioning is in Progress.

11th of July 2010
postension Testing at Level 24 & block work & plaster work & MEP work ,fire fighting & alarm system testing & commisioning is in Progress.

8th of July 2010
Curing & Pre stressing of postension at Level 24 & block work & plaster work & MEP work ,fire fighting & alarm system testing & commisioning is in Progress.

7th of July 2010
Curing at Level 24 & block work & plaster work & MEP work ,fire fighting & alarm system testing & commisioning is in Progress

6th of July 2010
Curing at Level 24 & block work & plaster work & MEP work ,fire fighting & alarm system testing & commisioning is in Progress

5th of July 2010
Curing at Level 24 & block work & plaster work & MEP work ,fire fighting & alarm system testing & commisioning is in Progress

4th of July 2010
Curing at Level 24 & block work & plaster work & MEP work ,fire fighting & alarm system testing & commisioning is in Progress.

3rd of July 2010
Casting & Curing at Level 24 is in Progress.

3rd of June 2010
Slab leveling & steel fixing at level 23 & block work & plaster work & MEP work ,fire fighting & alarm system testing & commisioning is in progress.

2nd of June 2010
Slab leveling & steel fixing at level 23 & block work & plaster work & MEP work ,fire fighting & alarm system testing & commisioning is in progress.

1st of June 2010
Doka system checking & steel fixing at level 23 & block work & plaster work & MEP work ,fire fighting & alarm system testing & commisioning is in progress.

31th of May 2010
Doka system checking & steel fixing at level 23 & block work & plaster work & MEP work ,fire fighting & alarm system testing & commisioning is in progress.

30th of May 2010
Doka system checking & steel fixing at level 23 & block work & plaster work & MEP work ,fire fighting & alarm system testing & commisioning is in progress.

27th of May 2010
Doka system checking & steel fixing at level 23 & block work & plaster work & MEP work ,fire fighting & alarm system testing & commisioning is in progress.

26th of May 2010
Doka system checking & steel fixing at level 23 & block work & plaster work & MEP work ,fire fighting & alarm system testing & commisioning is in progress.

25th of May 2010
Doka system checking & Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

24th of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

23th of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

20th of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

19th of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

18th of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

17th of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

16th of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

13th of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

12th of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

11th of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

10th of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

09th of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

06th of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

05th of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

04th of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

03rd of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

02nd of May 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

29th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

28th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

27th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

26th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

25th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

22th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

21th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

20th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

19th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

18th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

15th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

14th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

13th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

12th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

11th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

08th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

07th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

06th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

05th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

04th of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

01st of April 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

31th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

30th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

29th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

28th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress

25th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

24th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

23th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

22th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

18th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

17th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

16th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

15th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

14th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

11th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

10th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

09th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

08th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

07th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

04th of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

03rd of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

02nd of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

01st of March 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

•28th of February 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

•25th of February 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

•24th of February 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

•23th of February 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

•22th of February 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

•21th of February 2010
Block Work & plaster work & MEP work,fair fighting & alarm system installation Is in Progress.

•18th of February 2010
Block Work & plaster work & MEP work Is in Progress.

•17th of February 2010
Block Work & plaster work & MEP work Is in Progress.

•16th of February 2010
Block Work & plaster work & MEP work & Fire rated door installation Is in Progress

•15th of February 2010
Block Work & plaster work & MEP work & Fire rated door installation Is in Progress

•14th of February 2010
Block Work & plaster work & MEP work & Fire rated door installation Is in Progress

•09th of February 2010
Block Work & plaster work & MEP work & Fire rated door installation Is in Progress.

•08th of February 2010
Block Work & plaster work & MEP work & Fire rated door installation at 12th floor Is in Progress.

•07th of February 2010
Block Work & plaster work & MEP work & Fire rated door installation at 12th floor Is in Progress.

•04th of February 2010
Block Work & plaster work & MEP work & Fire rated door installation at 12th floor Is in Progress.

•03rd of February 2010
Block Work & plaster work & MEP work & Fire rated door installation at 12th floor Is in Progress.

•02nd of February 2010
Block Work & plaster work & MEP work & Fire rated door installation at 11th floor Is in Progress.

•01st of February 2010
Block Work & plaster work & MEP work & Fire rated door installation at 10th floor Is in Progress.

•31st of January 2010
Ground Floor Block Work & plaster work & MEP work & Fire rated door installation at 10th floor Is in Progress.

•28th of January 2010
Ground Floor Block Work & plaster work & MEP work & Fire rated door installation at 10th floor Is in Progress.

•27th of January 2010
Ground Floor Block Work & plaster work & MEP work & Fire rated door installation at 10th floor Is in Progress.

•26th of January 2010
Ground Floor Block Work & plaster work & MEP work & Fire rated door installation at 10th floor Is in Progress.

•25th of January 2010
Ground Floor Block Work & plaster work & MEP work Is in Progress.

•24th of January 2010
Ground Floor Block Work & plaster work & MEP work & Stair case work GF. to FF Is in Progress& Fair Fighting pump has arrived to the wind site.

•21th of January 2010
Ground Floor Block Work & plaster work & MEP work & Stair case work GF. to FF Is in Progress.

•20th of January 2010
Ground Floor Block Work & plaster work & MEP work Is in Progress.

•19th of January 2010
Ground Floor Block Work & plaster work & MEP work Is in Progress.

•18th of January 2010
Ground Floor Block Work & plaster work & MEP work Is in Progress Also today second part of Elevators and Equipments has arrived in the Wind sites which are been unloading right now.

•17th of January 2010
Ground Floor Block Work Is in Progress &. The Fire Fighting pump has arrived in Jebel Ali Port and in one or two days will be release from the Port Authority and after the release it will go to the Wind Sites.After the Fire Fighting Pumps has been installed we will going to get COC III permit ,the last 2/3 slabs work progress has been done by undertaking letter.In Wind 1 slab has been inspecteded by Jafza and ready for casting and We waiting for COC III inspection. Also today Elevators and Equipments has arrived in the Wind sites which are been unloading right now

•14th of January 2010
Ground Floor Block Work Is in Progress.

•13th of January 2010
Ground Floor Block Work Is in Progress.

•12th of January 2010
Ground Floor Block Work Is in Progress.

•11th of January 2010
Ground Floor Block Work Is in Progress.

•10th of January 2010
Ground Floor Block Work Is in Progress.

•7th of January 2010
Ground Floor Block Work Is in Progress.

•23th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.

•22th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.

•21th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.

•20th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.

•17th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.

•15th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.

•14th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24 & wind material is received

•12th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24 & wind material is received.

•10th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24 & wind material is received.

•9th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.

•8th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.

•7th of December 2009
Top bar installation & ssk work & mep work is in progress at level 24.

•6th of December 2009
Temporary Fire Fitting I& postention work is in progress at level 24.

•1st of December 2009
Mep work & steel fixing & postention work is in progress.

•30th of November 2009
Mep work & steel fixing & postention work is in progress.

•29th of November 2009
Mep work & steel fixing & postention work is in progress.

•25th of November 2009
Steel Fixing & MEP Work at t level 24(+60.37) is in Progress.

•19th of November 2009
Steel Fixing & MEP Work at t level 24(+60.37) is in Progress.

•18th of November 2009
Steel Fixing & MEP Work & SSK work at t level 24(+60.37) is in Progress.

•15th of November 2009
Beam installation at level 24(+60.37) is in Progress.

•12th of November 2009
Beam installation at level 24(+60.37) is in Progress.

•11th of November 2009
Beam installation at level 24(+60.37) is in Progress.

•10th of November 2009
Beam installation at level 24(+60.37) is in Progress.

•8th of November 2009
Beam installation at Level 24(+60.37) is in Progress.

•2nd of November 2009
Doka System Installation at Level 24(+60.37) is in Progress.

•1st of November 2009
Doka System Installation at Level 24(+60.37) is in Progress.

•29th of October 2009
Doka System Installation at Level 24(+60.37) is in Progress.

•28th of October 2009
Doka system installation at Level 24(+60.37) & Core wall De Shuttering at Level 23 (+59.40) to Level 24(+60.37 is in Progress.

•27th of October 2009
Doka system installation at Level 24(+60.37) & Core wall De Shuttering at Level 23 (+59.40) to Level 24(+60.37 is in Progress.

•26th of October 2009
Doka system installation at Level 24(+60.37) is in Progress & Core Wall Casting Will be done at 10 pm.

•25th of October 2009
Doka system installation at Level 24(+60.37) is in Progress.

•22th of October 2009
Slab Form Work at Level 24(+60.37) is in Progress.

•21th of October 2009
Core wall Shuttering at Level 23 (+59.40) to Level 24(+60.37) is in Progress.

•20th of October 2009
Core wall Shuttering at Level 23 (+59.40) to Level 24(+60.37) is in Progress.

•19th of October 2009
Core wall Shuttering at Level 23 (+59.40) to Level 24(+60.37) is in Progress.

•18th of October 2009
Core wall Shuttering at Level 23 (+59.40) to Level 24(+60.37) is in Progress.

•15th of October 2009
Column De Shuttering at Level 23 (+59.40) to Level 24 (+60.37) & Core wall Installation at Level 23 (+59.40) to Level 24(+60.37) is in Progress.

•14th of October 2009
Column Casting at Level 23 (+59.40) to Level 24 (+60.37) & Core wall Installation at Level 23 (+59.40) to Level 24(+60.37) is in Progress.

•13th of October 2009
Column Shuttering at Level 23 (+59.40) to Level 24 (+60.37) & Core wall Installation at Level 23 (+59.40) to Level 24(+60.37) is in Progress.

•12th of October 2009
Column Shuttering at Level 23 (+59.40) to Level 24 (+60.37) & Core wall Installation at Level 23 (+59.40) to Level 24(+60.37) is in Progress.

•11th of October 2009
Column Installation & Shuttering at Level 23 (+59.40) to Level 24 (+60.37) & Temporary Fire Alarm & Fire Fitting Installation is in Progress.

•08th of October 2009
Column Installation & Shuttering at Level 23 (+59.40) to Level 24 (+60.37) & Temporary Fire Alarm & Fire Fitting Installation is in Progress.

•07th of October 2009
Curing at Level 23 (+59.40) & Column Installation & Shuttering at Level 23 (+59.40) to Level 24 (+60.37) & Temporary Fire Alarm & Fire Fitting Installation is in Progress.

•06th of October 2009
Curing at Level 23 (+59.40) & Column Installation & Shuttering at Level 23 (+59.40) to Level 24 (+60.37) & Temporary Fire Alarm & Fire Fitting Installation is in Progress.

•04th of October 2009
Casting & Curing at Level 23 (+59.40) & Temporary Fire Fitting & Fire Alarm Installation is in Progress.

•01th of Octo.ber 2009
Column Pre Fabrication Level 23 (+59.40) to Level 24 (+60.37)& Temporary Fire Fitting & Fire Alarm Installation is in Progress.

•30th of September 2009
Top Mesh Installation& MEP Work at Level 23 (+59.40) & temporary fire rated door installation is in Progress.

•29 th of September 2009
Top Mesh Installation& MEP Work at Level 23 (+59.40) & temporary fire rated door installation is in Progress.

•28 th of September 2009
Top Mesh Installation& MEP Work at Level 23 (+59.40) & temporary fire rated door installation is in Progress.

•27 th of September 2009
Top Mesh Installation& MEP Work at Level 23 (+59.40) & temporary fire rated door installation is in Progress.

•24 th of September 2009
Top Mesh Installation& MEP Work at Level 23 (+59.40) & temporary fire rated door installation is in Progress.

•23 th of September 2009
Top Mesh Installation& MEP Work at Level 23 (+59.40) & temporary fire rated door installation is in Progress.

•22 th of September 2009
Bottom Mesh Installation& MEP Work at Level 23 (+59.40) & temporary fire rated door installation is in Progress.

•19 th of September 2009
Steel fixing & MEP Work at Level 23 / temporary fire rated door installation is in Progress.

•29 th of August 2009
Core wall Shuttering & Column Installation from Level 22 to Level 23 (+56.39 to +59.40) & Slab Removing from Level 21 to Level 23 (+53.38 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.

•27 th of August 2009
Core wall Shuttering from Level 22 to Level 23 (+56.39 to +59.40) & Slab Removing from Level 21 to Level 23 (+53.38 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.

•23 th of August 2009
Column Casting from Level 22 to Level 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.

•20 th of August 2009
Curing at Level 22 (+56.39) & Column Shuttering from Level 22 to 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.

•19 th of August 2009
Curing at Level 22 (+56.39) & Column Shuttering from Level 22 to 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.

•18 th of August 2009
Curing at Level 22 (+56.39) & Core Wall Installation from Level 22 to 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.

•17 th of August 2009
Curing at Level 22 (+56.39) & Column Installation from Level 22 to Level 23 (+56.39 to +59.40) & Core Wall Installation from Level 22 to 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.

•16 th of August 2009
Curing at Level 22 (+56.39) & Column Installation from Level 22 to Level 23 (+56.39 to +59.40) & Core Wall Installation from Level 22 to 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.

•14 th of August 2009
Casting & Curing at Level 22 (+56.39) & Temporary Fire Rated Door Installation Is in Progress.

•13 th of August 2009
Steel fixing & MEP Work at Level 22 (+56.39) & Column Installation from Level 22 to Level 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress & Slab 15th Casting Will be done to night.

•12 th of August 2009
Steel fixing & MEP Work at Level 22 (+56.39) & Column Installation from Level 22 to Level 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.

•11 th of August 2009
Steel fixing & MEP Work at Level 22 (+56.39) & Column Installation from Level 22 to Level 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.

•10 th of August 2009
Steel fixing & MEP Work at Level 22 (+56.39) & Column Installation from Level 22 to Level 23 (+56.39 to +59.40) & Temporary Fire Rated Door Installation Is in Progress.

•09 th of August 2009
Steel fixing at Level 22 (+56.39) & Temporary Fire Rated Door Installation Is in Progress.

•06 th of August 2009
Slab Fixing & Beam Installation at Level 22 (+56.39) & Temporary Fire Rated Door Installation Is in Progress.

•05 th of August 2009
Slab Fixing & Beam Installation at Level 22 (+56.39) & Temporary Fire Rated Door Installation Is in Progress.

•04 th of August 2009
Slab Fixing at Level 22 (+56.39) & Temporary Fire Rated Door Installation Is in Progress.

•03 rd of August 2009
Slab Fixing at Level 22 (+56.39) & Temporary Fire Rated Door Installation Is in Progress.

•02 nd of August 2009
Slab Fixing at Level 22 (+56.39) & Temporary Fire Rated Door Installation Is in Progress.

•30 th of July 2009
Slab Removing at Level 20 to Level 22 (+50.37 to+56.39) & Temporary Fire Rated Door Installation Is in Progress.

•29 th of July 2009
Slab Removing at Level 20 to Level 22 (+50.37 to+56.39) & Temporary Fire Rated Door Installation Is in Progress.

•28 th of July 2009
Core Wall De Shuttering at Level 21 to Level 22 (+53.38 to +56.39) & Slab Removing at Level 20 to Level 22 (+50.37 to+56.39) & Temporary Fire Rated Door Installation Is in Progress.

•27 th of July 2009
Column De Shuttering at Level 21 to Level 22 (+53.38 to +56.39) & Core Wall Shuttering at Level 21 to Level 22 (+53.38 to +56.39)& Temporary Fire Rated Door Installation Is in Progress & Core Wall Casting Will be Done Tonight.

•26 th of July 2009
Column De Shuttering at Level 21 to Level 22 (+53.38 to +56.39) & Core Wall Shuttering at Level 21 to Level 22 (+53.38 to +56.39)& Temporary Fire Rated Door Installation Is in Progress.

•23 th of July 2009
Column Shuttering at Level 21 to Level 22 (+53.38 to +56.39) & Core Wall Installation at Level 21 to Level 22 (+53.38 to +56.39) & Curing at Level 21 & Temporary Fire Rated Door Installation Is in Progress & Column Casting will be done Tonight.

•22 th of July 2009
Column Shuttering at Level 21 to Level 22 (+53.38 to +56.39) & Core Wall Installation at Level 21 to Level 22 (+53.38 to +56.39) & Curing at Level 21 & Temporary Fire Rated Door Installation Is in Progress.

•21 th of July 2009
Column Installation & Shuttering at Level 21 to Level 22 (+53.38 to +56.39) & Curing at Level 21 & Temporary Fire Rated Door Installation & Is in Progress.

•20 th of July 2009
Column Installation at Level 21 to Level 22 (+53.38 to +56.39) & Curing at Level 21 & Temporary Fire Rated Door Installation & Is in Progress.

•17 th of July 2009
Casting & Curing at Level 21 (+53.38) & Temporary Fire Rated Door Installation Is in Progress.

•16 th of July 2009
Top Bar Steel Fixing at Level 21 (+53.38) & Temporary Fire Rated Door Installation Is in Progress & Ready to Casting.

•15 th of July 2009
Top Bar Steel Fixing at Level 21 (+53.38) & Temporary Fire Rated Door Installation Is in Progress.

•14 th of July 2009
MEP Work & SSK Work & Top Bar Steel Fixing at Level 21 (+53.38) & Temporary Fire Rated Door Installation Is in Progress.

•13 th of July 2009
MEP Work & SSK Work & Top Bar Steel Fixing at Level 21 (+53.38) & Temporary Fire Rated Door Installation Is in Progress.

•12 th of July 2009
MEP Work & Bottom Mesh Steel Fixing at Level 21 (+53.38) & Temporary Fire Rated Door Installation Is in Progress.

•09 th of July 2009
MEP Work & Bottom Mesh Steel Fixing at Level 21 (+53.38) & Temporary Fire Rated Door Installation Is in Progress

•08 th of July 2009
MEP Work & Bottom Mesh Steel Fixing at Level 21 (+53.38) & Temporary Fire Rated Door Installation & Core Wall De Shuttering Level 20 to Level 21 (+50.37 to +53.38) Is in Progress.

•07 th of July 2009
MEP Work & Bottom Mesh Steel Fixing at Level 21 (+53.38) & Temporary Fire Rated Door Installation Is in Progress & Core Wall Shuttering Level 20 to Level 21 (+50.37 to +53.38) Is Finished & Ready for Casting.

•06 th of July 2009
Slab Fixing & MEP Work & Bottom Mesh Steel Fixing at Level 21 (+53.38) & Core Wall Shuttering Level 20 to Level 21 (+50.37 to +53.38) Temporary Fire Rated Door Installation Is in Progress.

•05 th of July 2009
Slab Removing from Level 19 to Level 21 (+47.36 to +53.38) & Slab Fixing at Level 21 & Core Wall Shuttering Level 20 to Level 21 (+50.37 to +53.38) Temporary Fire Rated Door Installation Is in Progress.

•02 nd of July 2009
Slab Removing from Level 19 to Level 21 (+47.36 to +53.38) & Temporary Fire Rated Door Installation Is in Progress

•01 st of July 2009
Slab Removing from Level 19 to Level 21 (+47.36 to +53.38) & Column De Shuttering at Level 20 to Level 21 (+50.37 to+53.38) & Temporary Fire Rated Door Installation Is in Progress.

• 30 th of June 2009
Curing at Level 20 (+50.37) & Core Wall Steel Fixing at Level 20 to Level 21 (+50.37 to+53.38) & Column De Shuttering at Level 20 to Level 21 (+50.37 to+53.38) & Temporary Fire Rated Door Installation Is in Progress.

• 29 th of June 2009
Curing at Level 20 (+50.37) & Core Wall Steel Fixing at Level 20 to Level 21 (+50.37 to+53.38) & Column Shuttering at Level 20 to Level 21 (+50.37 to+53.38) & Temporary Fire Rated Door Installation Is in Progress & Column Casting Will Be Done Tonight.

• 28 th of June 2009
Curing at Level 20(+50.37) & Core Wall Steel Fixing at Level 20 to Level 21 (+50.37 to+53.38) & Column Shuttering at Level 20 to Level 21 (+50.37 to+53.38) & Temporary Fire Rated Door Installation Is in Progress.

26 th of June 2009
Casting at Level 20(+50.37)

• 25 th of June 2009
Top Mesh Installation & Post Tension Work & MEP Work at Level 20(+50.37) Is Finished & Ready to Casting & Temporary Fire Rated Door Installation Is in Progress

• 24 th of June 2009
Top Mesh Installation & Post Tension Work & MEP Work at Level 20(+50.37) & Temporary Fire Rated Door Installation Is in Progress.

• 23 th of June 2009
Post Tension Work & MEP Work at Level 20 (+50.37) & Temporary Fire Rated Door Installation Is in Progress.

• 22 th of June 2009
Bottom Mesh Installation & MEP Work at Level 20 (+50.37) & Temporary Fire Rated Door Installation Is in Progress & Column Installation at Level 19 to Level 20 (+47.36 to+50.37) Is Finished.

• 21 th of June 2009
Slab Fixing & Bottom Mesh Installation & MEP Work at Level 20 (+50.37) & Temporary Fire Rated Door Installation & Column Installation at Level 19 to Level 20 (+47.36 to+50.37) Is in Progress.

• 18 th of June 2009
Slab Removing at Level 18 to Level 20 (+44.35 to +50.37) & Temporary Fire Rated Door Installation & Core Wall De Shuttering at Level 19 to Level 20 (+47.36 to+50.37) Is in Progress.

• 17 th of June 2009
Slab Removing at Level 18 to Level 20 (+44.35 to +50.37) & Temporary Fire Rated Door Installation Is in Progress , Core Wall Shuttering at Level 19 to Level 20 (+47.36 to+50.37) Is Finished Core wall Casting Will Be Done at 5 O'clock.

• 16 th of June 2009
Slab Removing at Level 18 to Level 20 (+44.35 to +50.37) & Temporary Fire Rated Door Installation Is in Progress.

• 15 th of June 2009
Curing at Level 19 (+47.36) & Core Wall Shuttering at Level 19 to Level 20 (+47.36 to +50.37) & Slab Removing at Level 18 to Level 20 (+44.35 to+50.37) & Temporary Fire Rated Door Installation Is in Progress.

• 14 th of June 2009
Curing at Level 19 (+47.36) & Slab Removing at Level 18 to Level 20 (+44.35 to+50.37) & Temporary Fire Rated Door Installation Is in Progress.

• 11 th of June 2009
Curing at Level 19 (+47.36) & Core Wall Shuttering at Level 19 to Level 20 (+47.36 to +50.37) & Column De Shuttering at Level 19 to Level 20 (+47.36 to +50.37) & Temporary Fire Rated Door Installation Is in Progress.

• 10 th of June 2009
Curing at Level 19 (+47.36) & Core Wall Installation at Level 19 to Level 20 (+47.36 to+50.37) & Column Shuttering at Level 19 to Level 20 (+47.36 to+50.37) & Temporary Fire Rated Door Installation Is in Progress.

09th of June 2009
Casting at Level 19 (+47.36) Is Finished & Curing at Level 19 (+47.36) & Core Wall Installation at Level 19 to Level 20 (+47.36 to+50.37) & Temporary Fire Rated Door Installation Is in Progress.

• 08th of June 2009
Cleaning of Slab at Level 19 (+47.56) & Ready to Casting & Core Wall Installation at Level 19 to Level 20 (+47.56 to+50.57) & Temporary Fire Rated Door Installation Is in Progress.

• 07th of June 2009
Steel Fixing at Level 19 (+47.56) & Core Wall Installation at Level 19 to Level 20 (+47.56 to+50.57) & Temporary Fire Rated Door Installation Is in Progress.

• 04th of June 2009
Steel Fixing & Post Tension Work at Level 19 (+47.56) & Core Wall Installation at Level 19 to Level 20 (+47.56 to+50.57) Is in Progress.

• 03rd of June 2009
Steel Fixing & Post Tension Work at Level 19 (+47.56) & Column & Core Wall Installation at Level 19 to Level 20 (+47.56 to+50.57) Is in Progress.

• 02nd of June 2009
Steel Fixing & Post Tension Work & MEP Work at Level 19 (+47.56) & Column Installation at Level 19 to Level 20 (+47.56 to+50.57) Is in Progress.

• 01st of June 2009
Steel Fixing & Post Tension Work & MEP Work at Level 19 (+47.56) & Column Installation at Level 19 to Level 20 (+47.56 to+50.57) Is in Progress.

• 31th of May 2009
Bottom Mesh Steel Fixing & Post Tension Work & MEP Work at Level 19 (+47.56) & Column Installation at Level 19 to Level 20 (+47.56 to+50.57) Is in Progress.

• 28th of May 2009
Slab Leveling & MEP marking at Level 19 (+47.56) Is in Progress.

• 27th of May 2009
Form Work Of Slab at Level 19 (+47.56) Is in Progress.

• 26th of May 2009
Form Work Of Slab at Level 19 (+47.56) Is in Progress.

• 25th of May 2009
Core Wall Casting & De Shuttering at Level 18 to level 19 (+44.35 to +47.56) & Form Work Of Slab at Level 19 (+47.56) Is in Progress.

• 24th of May 2009
Core Wall Shuttering at Level 18 to level 19 (+44.35 to +47.56) Is Finished & Ready for Casting & Form Work Of Slab at Level 19 (+47.56) Is in Progress

• 21th of May 2009
Core Wall Shuttering at Level 18 to level 19 (+44.35 to +47.56) & Form Work Of Slab at Level 19 (+47.56) Is in Progress.

• 20th of May 2009
Core Wall Shuttering at Level 18 to level 19 (+44.35 to +47.56) Is in Progress.

• 19th of May 2009
Column De Shuttering at Level 18 to level 19 (+44.35 to +47.56) & Aluminum Cladding & Glazing Sample installation Is in Progress.

• 18th of May 2009
Column Shuttering at Level 18 to level 19 (+44.35 to +47.56) &
Core Wall Installation at Level 18 to level 19 (+44.35 to +47.56) is finished & Columns Are Ready for the Casting.

• 17th of May 2009
Column Shuttering at Level 18 to level 19 (+44.35 to +47.56) & Core Wall Installation at Level 18 to level 19 (+44.35 to +47.56) is in Progress.

• 14th of May 2009
Casting & Curing at Level 18 (11th floor +44.35 )

• 13th of May 2009
Top Bar Steel Fixing & MEP Work is in progress & Post Tension Work at Level 18 (11th floor +44.35 ) & 11th floor is Ready for Casting.

• 12th of May 2009
Top Bar Steel Fixing & MEP Work is in progress & Post Tension Work at Level 18 (11th floor +44.35 ) & Column Installation at Level 18 to level 19 (+44.35 to +47.56) is Finished.

• 11th of May 2009
Bottom Mesh Steel Fixing & MEP Work & Post Tension Work at Level 18 (11th floor +44.35 ) & Column Installation at Level 18 to level 19 (+44.35 to +47.56) is in progress.

• 10th of May 2009
Slab Form Work Leveling & Bottom Mesh Steel Fixing & MEP Work & Post Tension Work at Level 18 (11th floor +44.35 ) & Column Installation at Level 18 to level 19 (+44.35 to +47.56) is in progress.

• 07th of May 2009
Slab Form Work at Level 18 (11th floor +44.35 ) & Column Installation at Level 18 to level 19 (+44.35 to +47.56) is in progress.

• 06th of May 2009
Slab Form Work at Level 18 (11th floor +44.35 ) is in progress.

• 05th of May 2009
Slab Form Work at Level 18 (11th floor +44.35 ) & Core wall De shuttering at Level 18 to level 19 (+44.35 to +47.56) is in progress.

• 04th of May 2009
Slab Form work at Level +44.35 (Level 18th, 11th Floor) & Core wall Shuttering & Casting at Level +41.34 to Level +44.35 is in Progress.

• 03rd of May 2009
Slab Form work at Level +44.35 (Level 18th, 11th Floor) & Core wall Shuttering at Level +41.34 to Level +44.35 is in Progress.

• 30th of April 2009
Slab Form work at Level +44.35 (Level 18th, 11th Floor) & Core wall Installation at Level +41.34 to Level +44.35 is in Progress.

• 29th of April 2009
Slab Form work at Level +44.35 (Level 18th, 11th Floor) & Core wall Installation at Level +41.34 to Level +44.35 is in Progress.

• 28th of April 2009
Slab Form work at Level +44.35 (Level 18th, 11th Floor) & Core wall Installation at Level +41.34 to Level +44.35 is in Progress.

• 27th of April 2009
Slab Form work at Level +44.35 (Level 18th, 11th Floor) is in Progress.

• 26th of April 2009
De shuttering of Vertical Elements Level 41.34 (Level 17th, 10th Floor) to 44.35 (Level 18th, 11th Floor).

• 23rd of April 2009
Concrete Casting of Vertical Elements Level 41.34 (Level 17th, 10th Floor) to 44.35 (Level 18th, 11th Floor).

•20th of April 2009
Concrete Casting of Slab Level at Level 41.34 (Level 17th, 10th Floor).

•12th of April 2009
Steel Fixing of Core wall at Level 41.34 is in Progress (Level 17th, 10th Floor).

• 9th of April 2009
Concrete Casting of Core wall Level 38.33 (Level 16th, 9th Floor) to 41.34 (Level 17th, 10th Floor).

• 1st of April 2009
Form work of Slab at Level 41.34 (Level 17th, 10th Floor).

• 28th of March 2009
Core wall Shuttering is in Progress.

• 22nd of March 2009
Concrete Casting of Vertical Elements Level 38.33 (Level 16th, 9th Floor) to 41.34 (Level 17th, 10th Floor).

• 19th of March 2009
Shuttering of Vertical Elements is in Progress.

• 18th of March 2009
Concrete Casting of Slab Level at Level 38.33 (Level 16th, 9th Floor).

• 15th of March 2009
Steel Fixing of Slab at Level 38.33 (16th) is in Progress.

• 10th of March 2009
Columns Installation Level 38.33 (16th) to 41.34 (17th) are Finished Today.

• 8th of March 2009
Steel Fixing at Level 38.33 (16th) is in Progress.

• 3rd of March 2009
Form work of Slab at Level 38.33 (16th) is in Progress.

• 26th of February 2009
Concrete Casting of Vertical Elements Between Level 35.32 (15th) to Level 38.33 (16th).

• 25th of February 2009
Shuttering of Vertical Elements Between Level 35.32 (15th) to Level 38.33 (16th).

• 23st of February 2009
Concrete Casting of Slab Level 35.32 (15th).

• 18th of February 2009
Steel Fixing of Slab Level 35.32 (15th) is in Progress.

• 17th of February 2009
Installation of Vertical Elements Between Level 35.32 (15th) to Level 38.33 (16th).

• 15th of February 2009
Form work of Slab Level 35.32 (15th) will be Completed Today.

Plastering in Retail area

Wind I
Block works on 2nd floor
Wind I

General View

Last Video Report